Pouring a Concrete Floor in a Post Frame Building - Hansen Buildings (2024)

Another great question from a loyal reader:

DEAR POLE BARN GURU: How would you install a concrete floor in one of your pole buildings. RICK in TOLEDO

DEAR RICK: Here is the chapter from the Hansen Pole Buildings Construction Manual:

Chapter 18: Concrete Slabs

While preference is to have building shell completed prior to pouring concrete slabs, at the very least, roof should be installed.

Building columns tend to grow “bull’s-eyes” in the presence of pre-mix concrete trucks. A completed building shell is far more resistant to potential damage. Pouring slabs with columns only in place, adds to the risk of one inadvertently being knocked out of plumb.

This section is not meant to provide the necessary instruction to pour a building slab. This is not because the task is beyond a novice’s abilities, although many do contract out this job. Pouring a slab is within most people’s abilities. However, unlike wood framing, which can be corrected if improperly constructed, work on a slab is “set in stone”. Due to this, and the fact so many local codes and practices apply to concrete slabs, we have only touched on this subject. If deciding to personally undertake, we suggest talking with local professionals to know what you are getting into. Have building inspector (usually a requirement in permitted situations) or a professional inspect work before pouring concrete. If under 100% confident, hire a professional to work alongside during the concrete pour.

If in “frost country” a sub-base 6” or thicker should be first placed across the site. To maintain frost-free soils sub-base should be such as no more than 5% (by weight) will pass the No. 200 sieve, and it is further desired no more than 2% be finer than .02 mm.

Prior to pouring, 2” to 6” of clean and drained sand or sandy gravel is spread below where concrete is to be poured. Mechanically compact fill to at least 90% of a Modified Proctor Density, so as not to cause slab to sink. ALWAYS install a good vapor barrier (such as A2V reflective insulation, available through Hansen Buildings) below any interior pour, to stop moisture from traveling up into slab through capillary action. Place 3” to 4” of clean and drained sand on top of the vapor barrier, to decrease differential drying shrinkage and floor curling. If not using fiber-mesh or similar reinforcement additives to concrete mixture, place wire mesh or rebar (reinforcing steel rods) in slab center to add rigidity to concrete to aid in minimizing cracking.

Insulation Underneath Concrete Slabs

Best product to use is A2V reflective insulation. Unroll reflective insulation over prepared site sand or gravel, with aluminum side facing ground (white side up). Overlap by 2” at seams. Run reflective insulation up skirt board inside by 6”. Seal seams with reflective insulation white vinyl tape or white duct tape. Pour concrete on top of reflective insulation.

Aluminum side faces away from the concrete as concrete’s high alkalinity attacks aluminum causing facing to degrade.

Adding sand over reflective insulation will facilitate water drainage during curing time and accelerate installation.

Local code will dictate such things as slab thickness (usually 4” nominal), wire mesh sizing, gravel or sand layer thickness, and size and rebar location. Many garage or shop slabs also have a center drain. In the event structural engineering for a concrete floor (or any concrete or other masonry footings, foundations, walls, or retaining walls) is required or requested by you, or a building official, this is outside our engineer’s scope.

On solid walls of building, pressure treated skirt board will serve as forms for pouring slab. In open wall areas, or across sliding or overhead doors, a 2×4 will need to be temporarily place as a form.

Prior to pouring a nominal 4” (3-1/2” actual completed) thick concrete slab in building, finished, graded compacted fill TOP will be even with skirt board BOTTOM. If a thicker floor is desired, excavate below skirt board bottom, by any slab thickness greater than 4”. In no case, will concrete floor top, be even with either top or skirt board bottom. Using any other measure for the concrete slab top, will result in wall steel and doors not properly fitting, as well as interior clear height loss.

In other terms – after the floor is poured, when standing inside building, approximately 3-3/4” of the skirt board will be visible above the top of the slab.

In the event a professional is hired to finish concrete, most often costs can be reduced by paying the local pre-mix company direct for the concrete. Many offer discounts for prompt payment, so do not be afraid to ask. On a properly leveled site, a pre-mix concrete yard will cover an 80 square feet area, nominally four inches thick.

Mike the Pole Barn Guru

Related Posts:

Insulating a Partially Climate Controlled BuildingInsulating a Partially Climate Controlled Post Fra...Raising a Ceiling, Foundation Wall Build, and an I...This Wednesday the Pole Barn Guru answers reader q...High Density Foam for Setting PostsThis is just wrong - in so many ways....As my ...
Pouring a Concrete Floor in a Post Frame Building - Hansen Buildings (2024)

FAQs

Can you put a concrete floor in an existing pole barn? ›

If you decide to pour your concrete after your building has been constructed, there is a potential risk for building damage. Your post frame columns tend to be “targets” for concrete trucks. Pouring slabs with columns only in place will add to the risk of one of them being knocked out of square.

Can you pour concrete after a metal building is installed? ›

It's possible to pour concrete after erecting a building. But this can lead to issues with condensation. That's especially true if you use heaters to artificially speed up the curing process. As concrete dries, a huge amount of moisture is released into the air.

When building a pole barn, do you pour the concrete first? ›

One of the most common questions our team is asked during the pole barn building process is whether or not the customer should have a concrete pad poured before starting construction. The short answer to this question is no.

Can you pour concrete in an existing building? ›

You can add a layer of concrete over an existing feature as long as you follow a few best practices to ensure the overlay concrete will adhere to the existing material properly. However, if the concrete structure has signs of damage, it's best to remove or repair it.

Can you put a second floor on a pole building? ›

This is a question we get fairly often. The short answer is yes, you can. However, there are several factors you'll need to consider as you think through this design option for your building.

How thick should a pole barn floor be? ›

Six inches of thickness should be more than adequate for areas where heavy equipment will be driven and parked. For lesser loads, four inches.

How long does concrete need to cure for metal building? ›

While many recommend waiting a full 60 days for a concrete slab to cure before building on top of it, there are some ways you can speed up the process and your project timeline.

What is the best foundation for a metal building? ›

Ideally, your metal building will rest on a concrete slab foundation or a few concrete strips around the outside base. A concrete slab is by far the most popular option, but you can use another material depending on your property's terrain.

What do you put between metal and concrete? ›

With strong adhesive properties, polyurethane sealants are commonly used to adjoin dissimilar materials such as metal trim to a concrete foundation.

How long do pole barns last in concrete? ›

40 - 60 years

How much gravel under concrete for pole barn? ›

ANSWER: We would recommend starting with a layer of #2 gravel as a base layer (typically 6” thick), then covering it with a layer of #53 stone and lime. The #53 gravel will “lock in” the #2 gravel, and create an excellent surface to drive on, and operate the equipment.

Does a pole barn slab need footers? ›

For a pole barn, consider using concrete footings that are large enough to withstand the building's weight, limiting the risk of settling and increasing stability.

Can you put new concrete over old cracked concrete? ›

You can put new concrete over old concrete. However, unresolved issues with your old concrete, such as cracks or frost heaves, will carry over to your new concrete if not taken care of. In addition, you must pour it at least 2 inches thick.

Can I put Quikrete over existing concrete? ›

Old concrete must be rigorously cleaned to ensure proper adhesion of QUIKRETE® Concrete Resurfacer to the old surface. A high strength pressure washer must also be used to completely clean the existing concrete.

Can you put a thin layer of concrete over concrete? ›

How thin can you pour concrete over concrete? Your new layer needs to be at least 2 inches thick. If it's any thinner than that, it'll easily crack under pressure and won't adequately bond to your surface.

Should a barn have a concrete floor? ›

1. Concrete. Concrete is a popular option, which attracts less dust and moisture. It can be a great base for keeping the barn floors level and clean.

Can you put a basem*nt in a pole barn? ›

Our concrete crew says: the answer is yes

With an experienced concrete crew, you can pour a basem*nt for a pole barn. It is not very typical to have a basem*nt under a post-frame building, however, it is possible and has been done before.

What can I use instead of concrete for pole barn? ›

A cost-effective option for pole barns is gravel flooring. It provides a stable base for storing equipment and other materials. One advantage of gravel is its permeability, which allows for water drainage and helps prevent moisture buildup under the barn.

Top Articles
Latest Posts
Article information

Author: Sen. Ignacio Ratke

Last Updated:

Views: 6585

Rating: 4.6 / 5 (56 voted)

Reviews: 95% of readers found this page helpful

Author information

Name: Sen. Ignacio Ratke

Birthday: 1999-05-27

Address: Apt. 171 8116 Bailey Via, Roberthaven, GA 58289

Phone: +2585395768220

Job: Lead Liaison

Hobby: Lockpicking, LARPing, Lego building, Lapidary, Macrame, Book restoration, Bodybuilding

Introduction: My name is Sen. Ignacio Ratke, I am a adventurous, zealous, outstanding, agreeable, precious, excited, gifted person who loves writing and wants to share my knowledge and understanding with you.